Project Description
The existing pool at Port Charlotte Beach Park will be replaced with a community pool suitable for lap swimming, aerobic exercise, and therapy. A new bathhouse will be constructed suitable for other special events. This is a 2020 Sales Tax Extension Tier 2 project with an anticipated allocation of $4.5 million. The pool was originally part of the Port Charlotte Beach Recreation Center, which was separated when the final list was prepared.
Project Location
4500 Harbor Blvd. Port Charlotte, FL 33952Project Impacts
Weather
Army Corps of Engineers
Florida Department of Environmental Protection
Fish & Wildlife Conservation
South West Florida Water Management District
Latest Updates
There was a Request For Proposals advertised on August 21, 2024, for a new consultant to design the Recreation center and the Pool House for Port Charlotte Beach. Proposals are due back to purchasing September 16, 2024. Shortlisting is scheduled for Oct. 4, 2024. Port Charlotte Beach project proposed consultant firm will go before the Board on November 12, 2024. for approval. The Board has approved Harvard Jolly as the new consultant for the Port Charlootte Beach project.
We are working with Construction Management at Risk Tandem Construction. The Demolition of restroom by the pool, pool & pool house, and center are ongoing at Port Charlotte Beach Recreation Center. So far, the restroom and center have been demolished. Contractor will start demoing pool and pool house next.
A kickoff meeting was held on January 7, 2025, with Harvard Jolly Architecture to discuss responsibilities, scheduling, and strategies on the best way to move forward with Port Charlotte Beach Recreation Center project.
Budget
Phase | Cost |
---|---|
Design | $262,000 |
Construction | $4,238,000 |
Total Budget | $4,500,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 10/01/2022 | 10/01/2022 | 10/01/2022 |
Design Development | 11/29/2024 | 08/29/2025 | |
Construction | 09/26/2025 | 09/30/2026 | |
Turnover & Closeout | 10/30/2026 | 12/30/2026 |
Project Phase
Design Development
Last Updated
01/17/2025
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Project Number
c722104
Sponsor Department
Community Services
Design Engineer/Architect
Harvard Jolly
Construction Contractor
Tandem Construction